Things Remembered Rolls Out Delta MCS
Download
the newsletter in which this article appears
Roll-out driven by reduced shrinkage, improved productivity
measured in pilot test
A careful pilot test of Delta MCS that began in October of last year
culminated in a full roll-out of the system last month at the Things Remembered
distribution center in North Jackson, Ohio. Things
Remembered, a $285M national retailer specializing in personalized
gifts with nearly 800 stores and three channels of distribution, called
upon VeriStitch to help improve monogram productivity and reduce inventory
lost to personalization errors. Good communication and planning coupled
with superb execution resulted in a Delta MCS solution with a high return
on investment. When installation was completed, 71 Meistergram 900XLC
machines were networked to a single Delta Network Server and coupled to
their mainframe-based order entry system.
Smooth roll-out the result of good planning
Working with the Things Remembered project team on the roll-out plan
was a pleasure. Shari Schrader, Director; Diane McCarty, Manager; and
Lee Damico, Production Lead; all of TR Direct, were appointed to take
ownership of the Delta MCS project. They followed our installation planning
documentation carefully, something we provide in advance of the actual
installation. Everything we requested was in place on our arrival and
we hit the ground running. By mid-week, the system was fully operational
with minimal disruption to the production floor schedule, no small matter
since the installation occurred in the midst of one of their production
peaks.
Another brilliant Things Remembered foresight that paid off in the roll-out
was to cycle all of their machine operators through the Delta MCS pilot
test pod of 6 machines throughout the pilot period. As soon as we had
machines connected to Delta MCS, operators were able to start using the
system immediately. This allowed us to monitor the system with a full
user population while we were still on site, adding to user confidence
in the stability of the system.
In a way, the installation was too smooth, almost to the point of boredom,
leaving the Things Remembered leadership team wondering if the real disaster
was still waiting to happen after we were off site. But they were disappointed
there too. Guess we'll just have to give good planning its due!
Pilot test meets shrinkage, productivity goals
As with any technology, customers are looking for tangible payback over
a reasonable period. Delta MCS delivered for Things Remembered in a big
way, and that is what drove the roll-out. The two areas Things Remembered
was looking for improvements in were shrinkage due to operator error and
productivity.
- Shrinkage Shrinkage due to operator error here means any item
that becomes non-saleable due to misspelled personalization, wrong design,
wrong thread color or any other operator caused error. Things Remembered
sets a maximum acceptable shrinkage limit; operators must perform below
that limit to be considered proficient. Results with Delta MCS? Operator-induced
shrinkage went to zero for the entire test cycle!
- Productivity Productivity here equates to a units per hour
(UPH) goal that is set for their operators. In their manual environment
(pre-MCS), the goal was set at 7 UPH with an entire staff average coming
in at 5 UPH. Initial results with Delta MCS? A 16% overall improvement
in productivity department wide coupled with a 30% overall improvement
in mispersonalization performance. It will be interesting to
see where Things Remembered sets their new UPH goals after accumulating
some experience with Delta MCS.
Delta MCS roll-out, just another Things Remembered success
While we were visiting Things Remembered, we couldn't help but notice
the huge banner trumpeting their recent qualification as an ISO 9001:2000
certified plant. Things Remembered is the first in its industry to achieve
such a certification. Based on our experience working with them, their
careful planning and cheerful teamwork, we're not surprised! Our thanks
go to Things Remembered, their leadership and project teams and all who
helped make the Delta MCS roll-out such a success.
|